BUILDING PERMIT FEES
This is a list of Building Permit Fees only. Other
Planning, Zoning, or Land Disturbance Fees may apply.
Click
here for the
complete Caroline County Planning and Community Development
Fee Schedule.
Residential Fee Schedule
Plan Review Accessory Structures
Commercial and Industrial Fee Schedule
Miscellaneous Fee Schedule
Construction Trailer Sales Trailer
Fuel Storage Tanks Water Storage Tanks
Additional Permit and Fee Information
Adopted June 12, 2012
|
Building Department Fees
|
||||||||||
|
|
|
|
Fees |
|||||||
|
§ 29-1. |
Fee Schedule |
|
||||||||
|
A. |
|
Caroline County building, electrical, mechanical and plumbing permit applicationfees shall be as follows: |
|
|||||||
|
|
|
|
|
|||||||
|
1. |
|
Residential Fee Schedule and Permits |
|
|||||||
|
|
|
|
|
|||||||
|
|
(a) |
Plan Review Deposits |
|
|||||||
|
|
[1] |
Plan Review Deposit, for a single family dwelling, Modular, Double-wide manufactured home, and single-wide manufactured home, of $200.00 shall be payable when application is submitted, which will be credited to the total cost calculated for the permits. Deposits shall not be refundable if the permits are not picked up within 90 days after approval. |
200.00 |
|||||||
|
|
|
|
|
|||||||
|
|
[2] |
Plan review deposit for
accessory structures, payable when application is submitted, which
will be credited to the total cost calculated for the permits.
Deposits shall not be refundable if the permits are not picked up
within 90 days after approval |
100.00 |
|||||||
|
|
(b) |
Plan Review fees as follows:
|
|
|||||||
|
|
[1] |
Residential Dwelling Units, Additions, Alterations, Manufactured Homes, and Industrialized Homes (modular) |
|
|||||||
|
|
|
(a) Per Square Foot - 1st Floor |
.15 |
|||||||
|
|
|
(b) Per Square Foot - 2nd Floor, finished basement |
.15 |
|||||||
|
|
|
(c) Per Square Foot - Unfinished Basement, Attached Garage, or Other Unfinished Area |
.15 |
|||||||
|
|
(d) Minimum Permit |
100.00 |
||||||||
|
|
|
(e) Revisions to building plans previously approved. |
75.00 |
|||||||
|
|
[2] |
Accessory Structures (Storage sheds over 200 sq. ft., Detached Garages, Workshops, underground structures, etc.)
|
|
|||||||
|
|
|
(a) Per Square Foot |
.12 |
|||||||
|
|
|
(b) Minimum Permit |
100.00 |
|||||||
|
[3] |
Electrical
|
|
||||||||
|
|
|
Per Dwelling Unit |
|
|||||||
|
|
|
(a) 200 amp or less |
75.00 |
|||||||
|
|
|
(b) More than 200 amp |
150.00 |
|||||||
|
|
|
(c) Over 5,000 sq. ft. |
.015/sq. ft. |
|||||||
|
|
|
(d) Per Addition, Alteration, Garage or Accessory Structure |
50.00 |
|||||||
|
|
|
(e) Per Service Upgrade or Change |
75.00 |
|||||||
|
|
|
(f) Manufactured Home |
50.00 |
|||||||
|
Plumbing
|
|
|||||||||
|
|
|
(a) Per Dwelling Unit (up to 5,000 square feet) |
75.00 |
|||||||
|
|
|
(b) Over 5,000 square feet) |
.015/sq.ft |
|||||||
|
|
|
(c) Per Addition, Alteration, Garage or Accessory Structure |
50.00 |
|||||||
|
|
|
(d) Manufactured Home |
50.00 |
|||||||
|
[5] |
Mechanical
|
|
||||||||
|
|
|
(a)
Per Dwelling Unit |
75.00 |
|||||||
|
|
(b) Over 5,000 square feet |
0.15/sq.ft |
||||||||
|
|
|
(c) Per Addition, Alteration, Garage or Accessory Structure |
50.00 |
|||||||
|
|
|
(d) Manufactured Home |
50.00 |
|||||||
|
|
|
(e) Fire Suppression System 0 - 2,000 square feet |
45.00 |
|||||||
|
|
|
(f) Fire Suppression System - Over 2,000 Square feet |
55.00 |
|||||||
|
|
|
(g) Change out or Replacement of Gas Furnace, Boiler, gas logs, or Fireplace
|
50.00 |
|||||||
|
Miscellaneous
|
|
|||||||||
|
|
|
(a) Replace Roof or Siding (not required but upon request) |
35.00 |
|||||||
|
|
|
(b) Brick Veneer |
35.00 |
|||||||
|
|
|
(c) Deck - up to 400 sq.ft. |
100.00 |
|||||||
|
|
|
(d) Deck - over 400 sq.ft. |
..25 sq. ft. |
|||||||
|
|
|
(e) Chimney |
40.00 |
|||||||
|
|
|
(f) Fireplace |
60.00 |
|||||||
|
|
(g) Docks |
50.00 |
||||||||
|
|
|
(h) Stoops /Porch |
50.00 |
|||||||
|
|
|
(i) Fence over 6 feet tall |
50.00 |
|||||||
|
|
|
(j) Generator |
100.00 |
|||||||
|
|
|
(k) Hot Tub |
100.00 |
|||||||
|
|
|
(j) Replace Water/Sewer Line |
50.00 |
|||||||
|
2. |
|
Commercial and Industrial Fee Schedule
|
|
|||||||
|
|
Plan Review Deposits |
|
||||||||
|
|
[1] |
Plan Review Deposit, for Commercial buildings under 5,000 square feet,, shall be payable when application is submitted, which will be credited to the total cost calculated for the permits. Deposits shall not be refundable if the permits are not picked up within 90 days after approval. Minor Alterations will require $100.00 deposit.
|
500.00 |
|||||||
|
|
[2] |
Plan Review Deposit, for a commercial building, 5,000 square feet or larger, shall be payable when application is submitted, which will be credit to the total cost calculated for the permits. Deposits shall not be refundable if the permits are not picked up within 90 days after approval. Minor Alterations will require $100.00 deposit.
|
750.00 |
|||||||
|
|
[3] |
Third party plan review fee will be charged at:
|
75.00/hr. |
|||||||
|
|
(b) |
Plan Review Fees are as follows:
|
|
|||||||
|
|
[1] |
New Construction
|
|
|||||||
|
|
|
(a) Plan Review Under 5,000 square feet |
225.00 |
|||||||
|
|
|
(b) Plan Review Over 5,000 square feet |
300.00 |
|||||||
|
|
|
(c) Per Square Foot - All Floor Area |
.17 |
|||||||
|
|
|
(d) Amendments to building plan previously reviewed or approved
|
100.00 |
|||||||
|
[2] |
Addition or Alteration
|
|
||||||||
|
|
|
(a) Plan Review Under 5,000 square feet |
125.00 |
|||||||
|
|
|
(b) Plan Review Over 5,000 square feet |
200.00 |
|||||||
|
|
|
(c) Per Square Foot – All Floor Area |
.17 |
|||||||
|
|
|
(d) Review of revisions to building plan previously reviewed or approved.
|
75.00 |
|||||||
|
Electrical
|
|
|||||||||
|
|
|
(a) Per Service - 200 Amps or Less |
125.00 |
|||||||
|
|
|
(b) Per Service - More than 200 Amps |
200.00 Min. |
|||||||
|
|
|
|
(50.00 per 100 amps) |
|||||||
|
|
|
(c) Per Square Foot of Floor Area |
.015/sq.ft. |
|||||||
|
|
|
(d) Minimum Permit |
125.00 |
|||||||
|
[4] |
Plumbing |
|
||||||||
|
|
|
(a) 0 up to 7,499 square feet |
125.00 |
|||||||
|
|
|
(b) 7,500 square feet or greater |
.015/sq.ft. |
|||||||
Mechanical
|
|
|||||||||
|
|
|
(a) 0 –- 4,000 Square Feet |
150.00 |
|||||||
|
|
|
(b) 4,001 - 20,000 Square Feet |
250.00 |
|||||||
|
|
|
(c) Plan review for over 20,000 square feet |
325.00 |
|||||||
|
|
|
Plus |
0.15/sq.ft. |
|||||||
Fire Suppression System
|
|
|||||||||
|
|
|
(a) Sprinkler New Construction |
2.50/head; 300.00 min. |
|||||||
|
|
|
(b) Sprinkler Alteration |
2.50/head; 100.00 min. |
|||||||
|
|
|
(c) Sprinkler Limted Area |
200.00 |
|||||||
|
|
|
(d) Type 1 & 2 Hoods |
100.00/hood |
|||||||
|
|
|
(e) Fire Dampers |
15.00/damper; 600.00 min. |
|||||||
|
|
|
(f) Fire Suppression for Hood
|
100.00 |
|||||||
|
|
|
(g) Reinspection or Retest of Sprinkler Flow Test
|
100.00 |
|||||||
|
Cell Towers (Building, Electric & Plan Review)
|
|
|
||||||||
|
|
|
(a) New Construction (Single Tenant) |
1,850.00 |
|
||||||
|
|
|
(b) Co-location
|
1,350.00 |
|
||||||
|
3. |
|
Miscellaneous Fee Schedule
|
|
|
||||||
|
|
(a) |
Miscellaneous fees as follows:
|
|
|
||||||
|
|
Construction Trailer (includes all fees) |
250.00 |
|
|||||||
|
|
Sales Trailer (includes all fees) |
350.00 |
|
|||||||
|
Fuel Storage Tanks |
|
|
||||||||
|
|
|
(a) Up to 50,000 Gallons - Total Per Site |
125.00 |
|
||||||
|
|
|
(b) Over 50,000 Gallons - Total Per Site |
275.00 |
|
||||||
|
|
|
(c) Fuel Tank Removal - In-ground |
150.00 |
|
||||||
|
|
|
(d) Fuel Tank Removal - Above Ground |
100.00 |
|
||||||
|
|
[4] |
Water Storage Tanks |
100.00 |
|
||||||
|
[5] |
Swimming Pools (Includes Electrical & Mechanical Fees) |
|
|
|||||||
|
|
|
(a) Above Ground - Residential |
100.00 |
|
||||||
|
|
|
(b) In Ground - Residential |
250.00 |
|
||||||
|
|
|
(c) Public
|
350.00 |
|
||||||
|
Elevators |
|
|
||||||||
|
|
|
(a) Per Floor & Minimum Electrical |
75.00 |
|
||||||
|
TOP
|
[7] |
Signs |
|
|
||||||
|
|
|
(a) Per Sign - Non-Illuminated |
35.00 |
|
||||||
|
|
|
(b) Per Sign - Illuminated |
100.00 |
|
||||||
|
|
|
(c) Per Sign More than 20 feet Above Grade |
75.00 |
|
||||||
|
[8] |
Fire Alarms |
|
|
|||||||
|
|
|
|
100.00 |
|
||||||
|
|
|
|
Plus $10.00 Per Device |
|
||||||
|
[9] |
Demolition - per permit |
30.00 |
|
|||||||
|
[10] |
Amusement Devices |
|
|
|||||||
|
|
|
(a) Per Kiddie Ride |
15.00 |
|
||||||
|
|
|
(b) Per Major Ride |
35.00 |
|
||||||
|
|
|
(c) Per Spectacular Ride |
55.00 |
|
||||||
|
[11] |
Commercial Re-Roof |
150.00 |
|
|||||||
|
[12] |
Generator Commercial |
150.00 |
|
|||||||
|
[13] |
Tents |
100.00 |
|
|||||||
|
|
|
Tents w/Electric |
150.00 |
|
||||||
|
* |
Building Official reserves the right to assign fees for items not shown |
|
|
|||||||
|
|
|
|
|
|||||||
|
4. |
|
ADMINISTRATIVE FEES |
|
|||||||
|
|
|
|
|
|||||||
|
|
|
(a) Fast Trac Plan Review |
.04/sq ft per copy |
|||||||
|
|
|
(b) Plan Review for Lost Plans |
50.00. |
|||||||
|
|
|
(c) Modification of Code (Inspection only) |
50.00 |
|||||||
|
|
(d) Modification to the Code - Certificate issued by Building Official |
50.00 |
||||||||
|
|
|
(e) Stop Work Order/Notice of Violation |
200.00 |
|||||||
|
|
|
(f) Building Change of Use/Occupancy Load |
50.00 |
|||||||
|
|
|
(g) C/O Existing Building |
25.00 |
|||||||
|
|
|
(h) Evaluation of Existing Structure |
100.00 |
|||||||
|
|
|
(i) Appeal to Local Building Code Board of Appeals |
250.00 |
|||||||
|
|
|
(j) Post Construction Permit Fee (construction without permit) |
Twice the amount of the permit fee or $250.00 - whichever is greater |
|||||||
|
|
|
|
|
|||||||
|
|
||||
|
R2% State Levy Shall be applied to all Fees. |
|
|||
|
Reinspection Fee |
|
|||
| TOP | ||||
|
|
A reinspection fee of $100.00 will be charged for each failed inspection. This reinspection fee shall be paid within thirty (30) days of the invoice date. Failure to pay within the thirty (30) day billing period shall result in the suspension of all inspections until all reinspection fees that are due, are paid in full. No final inspection for the certificate of occupancy will be scheduled until all reinspection fees are paid in full to the Department of Inspections. |
|||
|
|
|
|
|
|
|
Refunds
|
|
|
||
|
When a permit is returned or becomes void due to inactivity or abandonment, the permit holder may return the permit along with a written request for a refund within six (6) months. A refund will be issued subject to the following: |
||||
|
|
|
|
|
|
|
|
|
|||
|
|
|
|||
|
|
|
|||
|
|
|
|||
|
|
|
|||
|
|
|
|||
|
Abandonment of Work
|
||||
|
Any permit shall become invalid if work on the site authorized by the permit is not commenced within six months after issuance of the permit, or if the authorized work on the site is suspended or abandoned for a period of six months after the time of commencing the work; however, permits issued for building equipment such as plumbing, electrical and mechanical work shall not become invalid if the building permit is still in effect. It shall be the responsibility of the permit applicant to prove to the building official that work has not been suspended or abandoned. Upon written request, the building official may grant one or more extension of time, not to exceed one year per extension. Permits that become invalid will be voided and the permit fee forfeited. The permit can be reinstated one time within six (6) months of issuance for a $75.00 fee. |
||||
|
|
|
|||
|
Revocation of Permit
|
||||
|
Any permit that has been inactive for more than six (6) months
shall be revoked and the permit fee forfeited. A new permit shall be
required prior to resumption of the project. |
||||